LIRR vows to meet deadline for positive train control crash-prevention technology

LIRR vows to meet deadline for positive train control crash-prevention technology

It has come all the way down to the wire for the Lengthy Island Rail Highway to finish set up of federally required crash-prevention expertise all through 305 miles of monitor by the tip of 2020, or it dangers large, each day fines.

However railroad officers vow that the undertaking will get performed on time.

With six weeks to go earlier than a Dec. 31 deadline from the Federal Railroad Administration, the brand new “optimistic practice management” system is up and operating in 98% of the LIRR’s territory, with set up completed late final month on the busy Jamaica hub.

The ultimate, five-mile stretch of territory — the railroad’s Harold Interlocking in Queens — is scheduled to return on line by the tip of this month. The railroad additionally has to resolve a compatibility challenge earlier than the deadline between its system and Amtrak’s, which operates on the LIRR’s tracks in Queens.

LIRR president Phillip Eng mentioned work on a decision “is progressing and nearing last phases.”

“The end line is in sight,” Eng mentioned at a gathering of the Metropolitan Transportation Authority Board on Wednesday. “We stay assured that we are going to achieve success an in compliance with the FRA deadline.”

Constructive practice management, also referred to as PTC, was ordered by Congress in 2008 — after a California practice crash — to forestall rail collisions. The system makes use of communications expertise put in in trains and alongside tracks to robotically decelerate or halt trains that violate indicators. The Nationwide Transportation Security Board has mentioned, during the last 10 years, PTC might have saved the lives of at the least 60 individuals killed in practice accidents — together with 4 who perished in a Dec. 2013 Metro-North Railroad derailment within the Bronx.

Greater than 60 different passengers had been harm in that accident, together with Steven Ciccone, who mentioned Friday that the MTA’s anticipated completion of PTC on its two commuter railroads — the LIRR and Metro-North — is “disgustingly too little, too late.”

“In fact, it’s fantastic and memorable that we’re now defending and saving lives going ahead, however you’ll be able to’t undo a tragedy. You may’t get these youngsters again their father or their mom,” mentioned Ciccone, 37, of Portsmouth, Virg., who suffered a number of accidents when his practice automobile got here off the tracks because it entered a curve, and rolled down an embankment.

Ciccone sued the MTA and reached an undisclosed settlement final yr. He stays doubtful that the PTC undertaking will probably be accomplished.

The LIRR has twice been granted extensions from an authentic 2015 federal deadline to put in PTC. Railroads in violation could possibly be hit with fines of as a lot as $28,000 a day.

The FRA in a quarterly report printed Wednesday mentioned that PTC is operational in 99.6% of the practically 58,00 miles of tracks all through the U.S. Of the 40 railroads lined beneath the legislation, the FRA considers one is susceptible to lacking the Dec. 31 deadline — New Jersey Transit, which shares Penn Station with the LIRR and Amtrak.

Eleven railroads have accomplished set up of PTC programs, the FRA mentioned.

“I’m extremely happy with the intensive collaborations we’ve solid. As soon as full, railroads, rail staff, and rail passengers will all profit from this transformational accomplishment in railroad security,” mentioned Ronald Batory, administrator for the FRA, which final month accredited the LIRR’s PTC “security plan” — one other key milestone in assembly the federal mandate.

The LIRR’s eleventh-hour progress follows years of delays, value overruns, and botches within the design and set up of the expertise. After spending years unsuccessfully petitioning for an exemption from the federal legislation, the MTA lastly employed an organization to hold out its PTC undertaking in Nov. 2013 — 5 years after the federal legislation was handed, and simply two years earlier than the unique deadline.

Congress moved that deadline to Dec. 2018, after which to Dec. 2020, for railroads that had made ample progress.

The LIRR hit one other main snag final yr when its PTC contractor, a three way partnership of Bombardier Transportation/Siemens Rail Automation, revealed that it recalled lots of of “undercar scanner antennas” put in on trains as a result of they weren’t correctly calibrated.

Carl Berkowitz, a Moriches-based railroad security skilled, mentioned that, if the LIRR had accomplished the undertaking earlier “some accidents may need been prevented.” However he mentioned the delays might have had the unintended advantage of equipping the railroad with extra trendy expertise.

Berkowitz famous that PTC won’t deal with some of the persistent security issues — accidents involving trespassers or autos on tracks and at grade crossings — however it’s going to go a great distance in stopping accidents attributable to operators violating indicators and pace limits.

“It takes numerous the human issue out of the fingers of the practice operators, and into the fingers of expertise,” Berkowitz mentioned. “It’s not probably the most good system, nevertheless it’s higher than no system in any respect.”

MTA Chairman Patrick Foye on Wednesday steered a few of the hurdles encountered by the authority’s two railroads had been the results of the federal authorities being overly inflexible in its requirement for a selected crash-prevention system — overwhelming the comparatively new PTC design and manufacturing trade, and driving up prices.

Between its two railroads, PTC is costing the MTA about $1.15 billion, principally funded by way of a federal mortgage.

“Having all people undergo the revolving door on the similar time, I believe created leverage on the a part of the trade that resulted … in much less innovation,” mentioned Foye, including that the company is assessing the “classes realized” from the 12-year-long PTC effort. “On the finish of the day, they obtained it performed.”